Trade paper

Markets Texas Capital puts Sands China's 2028 Macau earnings just under US$2.28 billion.

Operators

Kangwon Land's second casino has a builder, at KRW74.1 billion.

A 2024 filing put the investment at KRW179.6 billion and the end at December 2027. Twenty-three months from an October 2026 selection lands in September 2028.

bookmaker.solutions

A half-finished casino room with a crimson felt table, a stack of emerald chips under a brass lamp, timber and a sawhorse on the carpet, and magenta and teal light down the hall.
Our picture. It is not a photograph from the source. The frame is this paper's mark.
The contract
KRW74.1 billion. Inside Asian Gaming prints US$55.1 million. The Herald Business prints about 74.1 billion won and $54.6 million. Dividing the won by each dollar figure gives KRW1,345 and KRW1,357 to the dollar. The stakes are 65, 20 and 15 percent. Applied to KRW74.1 billion they are KRW48.165 billion, KRW14.82 billion and KRW11.115 billion, which add back to KRW74.1 billion.
The building
Two floors below ground and four above, on the Kangwon Land site in Jeongseon, plus work on existing tourism lodging and entertainment. The duration is about 23 months. The lead bidder was ranked first in October 2026.
The 2024 sum
KRW179.6 billion, printed as $128 million. That is KRW105.5 billion above the contract. The contract is 41.3 percent of KRW179.6 billion. Asia Gaming Brief also prints a development plan of KRW2.5 trillion. Inside Asian Gaming's November account prints a KRW3 trillion plan as US$1.9 billion.
The floor
Asia Gaming Brief's account of the filing: casino area from 14,512 square meters to 20,260, a rise of 5,748. Tables up 50, to 250. Machines from 1,360 to 1,610, a rise of 250. Inside Asian Gaming's account of that filing prints the facility at 16,161 square meters and machines from 1,560 to 1,860.
The date
Asia Gaming Brief: construction from November 2024 to December 2027, 37 months. Inside Asian Gaming, the same week: a start that month, December 2024, and three years, to December 2027. A 23-month duration beginning on or after October 2026 ends in September 2028 or later, nine months after December 2027.

Shinyoung C&D is the lead contractor for a second gaming floor at Kangwon Land, the only casino in South Korea where residents may play. Inside Asian Gaming reported the appointment on 11 November. The price it prints is KRW74.1 billion, converted to US$55.1 million. The Herald Business, a day earlier, prints about 74.1 billion won and converts that to $54.6 million. Dividing KRW74.1 billion by US$55.1 million gives KRW1,345 to the dollar. Dividing it by $54.6 million gives KRW1,357. The gap between the two dollar figures is $0.5 million, which is 0.9 percent of the larger one. The Herald’s English page says the translation was machine-assisted. This paper did not open the Korean article that page links. The won, the stakes and the floor count are the same in both English accounts.

The job is a casino floor of two levels below ground and four above, on the resort site in Jeongseon-gun, plus renovation of existing tourism lodging and entertainment. Shinyoung holds 65 percent of the joint venture, Seorim General Construction 20 percent and Daehwa Construction 15 percent. Those shares add to 100. Applied to KRW74.1 billion they are KRW48.165 billion, KRW14.82 billion and KRW11.115 billion, and those three add back to the KRW74.1 billion. The Herald spells the lead firm Shinyang. Inside Asian Gaming spells it Shinyoung. Both say the firm ranked first under the comprehensive-evaluation tender run by the Public Procurement Service. The Herald says that ranking was last month, which from a 10 November report is October 2026. Work is put at about 23 months. Neither paper gives a bid number. This paper did not open the procurement notice.

The contract is not the investment figure filed two years ago. On 3 December 2024 Inside Asian Gaming reported a Monday filing that put the second-casino investment at KRW179.6 billion, converted to US$128 million. Asia Gaming Brief, the same day, reported the same won figure and the same dollar figure from a filing that Monday, and called the purpose a less crowded floor. KRW179.6 billion is KRW105.5 billion more than KRW74.1 billion. The contract is 41.3 percent of the filing’s investment. The two sums are not the same scope on the page. The 2026 contract, in both new accounts, includes renovation of lodging and entertainment as well as the new floor. The 2024 investment, in both old accounts, is the sum for the second casino site. This paper did not open the filing.

The place of the building is also told twice. Inside Asian Gaming in December 2024 put the facility across floors of the High1 Grand Hotel main tower, at 16,161 square meters, with a start that month and a finish in December 2027, three years on. Asia Gaming Brief put it at B1, B2 and the ground floors of that tower, and put the construction period at November 2024 to December 2027. November 2024 to December 2027 is 37 months. The November 2026 accounts describe a six-level building on the resort site. They do not repeat the tower as the address of this contract.

The gaming area in the two 2024 reports does not match. Asia Gaming Brief says the filing takes the casino from 14,512 square meters to 20,260. The difference is 5,748 square meters, 39.6 percent of the smaller area. Tables rise by 50, to 250. Machines go from 1,360 to 1,610, a rise of 250, which is 18.4 percent. Inside Asian Gaming’s report of that filing does not print 14,512 or 20,260. It prints 16,161 square meters for the facility, tables from 200 to 250, and machines from 1,560 to 1,860. That machine pair is 200 higher at each end, and the increase is 300 rather than 250.

Inside Asian Gaming on 11 November prints a footprint of 14,513 square meters rising to 20,261, and 50 more tables with 250 more machines, and it points the 2028 completion at its own 17 June 2026 report. That June report gives 14,513 to 20,261, tables from 200 to 250, and machines from 1,360 to 1,610, as the figures of a Samsung Securities analyst, not as cells from the filing. The area pair is one square meter above Asia Gaming Brief’s pair at each end. The increase is the same 5,748. The machine increase of 250 matches Asia Gaming Brief and the June analyst, and it does not match the 300 in the December 2024 Inside Asian Gaming report.

The calendar has moved with the builder. Asia Gaming Brief’s window runs from November 2024 to December 2027. From November 2024 to the October 2026 selection is 23 months, the same length as the contract now described. Inside Asian Gaming’s December 2024 start is December 2024, one month later, which is 22 months before October 2026, and its finish is still December 2027. A duration of 23 months that begins on or after that October selection ends in September 2028 or later. September 2028 is nine months after December 2027. Neither new report says the 23 months have already started, so the arithmetic is a bound, not a completion date. The June 2026 analyst note expected the second casino to be open in 2028. That year matches a job measured from the 2026 selection. It does not match December 2027.

The same November article converts a wider plan, which it calls K-HIT, at KRW3 trillion to US$1.9 billion. Dividing those two figures gives KRW1,579 to the dollar, not the KRW1,345 implied by its own contract conversion. At the contract rate, KRW3 trillion is US$2.23 billion. At the plan’s rate, KRW74.1 billion is US$46.9 million. Asia Gaming Brief in 2024 printed the wider plan as KRW2.5 trillion, or $1.78 billion, which is neither KRW3 trillion nor US$1.9 billion. Inside Asian Gaming now also names a longer aim of 13 million visits a year and KRW3.5 trillion of annual sales. No document opened for this note sets those two targets.

Asia Gaming Brief prints equity capital of KRW3.67 trillion next to the KRW179.6 billion. Inside Asian Gaming prints the US$128 million as 4.88 percent of the company’s equity. KRW179.6 billion is 4.89 percent of KRW3.67 trillion. Taking 4.88 percent of KRW3.67 trillion gives KRW179.1 billion, KRW0.5 billion under the investment figure. The filing would settle which base was meant. It was not opened.

This paper’s note of 9 November recorded that Kangwon Land’s own earnings note names a second casino among the work underway, beside the room renovation. The procurement result is the priced contract for a builder. The room timetable in that earlier note is a separate schedule.

Sources

  1. Inside Asian Gaming, 11 November 2026
  2. The Herald Business, 10 November 2026
  3. Inside Asian Gaming, 3 December 2024
  4. Asia Gaming Brief, 3 December 2024
  5. Inside Asian Gaming, 17 June 2026